Construction Tracking & Roadmap

Timeline & Construction Progress

Full transparency for partners, investors, and the board. Track physical-financial progress and target dates for each stage of the UniNeon TCC Data Center deployment.

Métrica Consolidada

Overall Project Progress

Weighted average of physical progress and deployment across the 6 strategic stages.

40%Completed Progress

1. Project Area Incorporation

Concluído

Land use assignment procedures at UNIVEM/Marília Campus, environmental licenses, and SPV registration.

Estimated Start11/1/2025
Estimated Completion2/28/2026
Completed Progress100%

2. Financial Investment Capture

Blended Finance structuring (BNDES Finem, FINEP, Private Equity, and Receivables Tokenization).

Estimated Start1/15/2026
Estimated Completion8/30/2026
Completed Progress65%

3. Structural Data Center Construction

Heavy civil works (Built-to-Suit), safe room construction, thermal containment, and Tier III/IV physical infrastructure.

Estimated Start4/1/2026
Estimated Completion2/28/2027
Completed Progress35%

4. Energy Resource Deployment (Grid)

Dedicated substation, local utility high-voltage connection, and N+1 generator and UPS redundancy.

Estimated Start6/1/2026
Estimated Completion4/30/2027
Completed Progress20%

5. Energy Resource Deployment (Photovoltaic)

Construction of the 20 MW Solar Plant by Domotyk and integration of the BESS battery storage system.

Estimated Start7/1/2026
Estimated Completion5/31/2027
Completed Progress15%

6. Computing Infrastructure (Racks, Comms & Servers)

Assembly of Meet-Me Rooms, structured fiber cabling, high-density racks, and AI clusters.

Estimated Start10/1/2026
Estimated Completion8/31/2027
Completed Progress5%