Technical Fact Sheet & Fundraising
Financial breakdown, ROI metrics, and equity quota reservation for the full deployment of 20 operational modules.
Offering Status (Bookbuilding)
0.00% Raised
Asset Overview
- Strategic Location:UNIVEM Campus, Marília-SP
- Target Classification:TIER III (ANSI/TIA-942)
- Structural Model:Transportable Outdoor Modules
- Planned Scalability:Up to 20 blocks/modules of 1 MW IT
- Final Capacity (Racks):1,040 IT & AI Racks
Modular Project Perspective

Hover over the image to explore details in zoom.
Capital Structure (CAPEX)
Breakdown for full deployment (20 Modules).
Item 1 — Administrative HQ, Paving, and Security Gate
Facility for up to 60 staff, paved internal roads, and 24/7 vehicle access control.
Item 2 — Power Substation
Dedicated 63 MW power substation.
Item 3 — Outdoor Modular Data Center (20 Modules of 1MW IT)
Total capacity of 20 MW IT. Each module includes a Data Hall with 52 racks, 1 MW Electrical Room, 02 modular UPS3, 1MW cooling, ELV systems, integration, testing, and transport.
Item 4 — Full Warranty / Support (Annual OPEX)
Annual preventive and corrective support contract (R$ 3,465,000.00 per module/year).
Item 5 — Energy Availability / Cost (Annual OPEX)
Annual utility contract for 24/7 power supply (R$ 13,666,666.67/month, approx. R$ 683,333.33/month per 100% active module).
Item 6 — Servers (High Density & AI)
For the 1040 total Racks: 50% traditional computing (25kVA, ~20 servers/rack) and 50% AI (40kVA, 4 GPU servers/rack).
Profitability Projection (ROI)
Colocation-Based Revenue Model
Estimated 12% to 15% p.a.
Monetizable Racks
Projection per R$ 100k
Analytical Note: Operational viability is structured around high-density Colocation contracts, ensuring cash flow stabilization and a Cap Rate superior to traditional real estate. The model enables consistent dividend distribution while protecting investor capital under institutional governance.
Expression of Interest (Equity Partner)
Complete the secure form below to receive the Memorandum of Understanding and initiate the quota subscription process for the UniNeon TCC project.